Monday, December 23

TCN Assures Maiduguri, Others will Get Electricity Restored in 2 Weeks

By Seun Adams

The Transmission Company of Nigeria (TCN) has assured that it is working assiduously to complete a transmission line by-pass

along the Damaturu-Maiduguri 132kV transmission line route, to provide a temporary source of power supply to Maiduguri and environs.

The General Manager, Corporate Affairs for the Company, Mrs. Ndidi Mbah, said the transmission line would be completed in two weeks to enable TCN to restore supply to Maiduguri and its environs.

According to her, the Acting Managing Director of TCN, Engr. Sule Abdulaziz gave this assurance weekend during an inspection tour of the site of the incident where reconstruction works for the new foundation for the towers have commenced. He also inspected the temporary by-pass transmission line project, which has reached an advanced stage.

According to him, following the damage of tower T159 which pulled down towers T160 and T161 along the same transmission line route recently, work on the transmission line diversion became necessary as the replacement of the permanent towers would take a little longer to complete and there was need to urgently meet the power supply need of electricity consumers in the affected areas.

She said the acting MD further explained that work on the by-pass for temporary diversion of electricity would be completed first, as quickly as possible, while for the permanent tower structure which is on-going, the engineers will need to take more time to properly reconstruct and mount new replacement towers.

Abdulaziz noted, “We are here at the site of the incident on the outskirts of Maiduguri, behind me is one of the towers that was vandalized. We are here with all our contractors who are already working on both projects. We have bought all the materials they require to do the work and would continue to bring in the rest from Maiduguri town in batches. On the other side you can see the diversion we are already putting in place, which is important to enable us supply the Maiduguri people with light as quickly as possible”.

The MD assured that TCN will complete the permanent reconstruction work on the towers very soon, to make sure that power supply is restored. Meanwhile, for the by-pass which would provide urgent relief, he said that if there are no interruptions, it will be completed in two weeks’ time. Already, materials, workers and combined team of security personnel required at the site to facilitate progress of work had been deployed. He thanked the security agencies and appealed to them to continue to support TCN to enable the company complete the task quickly.

He expressed his profound appreciation to the Governor of Borno State Prof. Babagana Zulum, whom he commended for the zeal and obvious commitment to resolving the power challenge in his state. The MD expressed satisfaction with the progress of work at the site, noting that Governor Zulum has continued to give TCN all the necessary support it required which has enabled the company continue with the project inspite of security challenges.

 

Leave a Reply

Your email address will not be published. Required fields are marked *